Starter Cloudscape Starter Kit

Project Phase

Duration

On-boarding + Strategy Call 

3 days

Data Gathering + Receive Data  

2 weeks 

Data Implementation 

3 days 

Back End/ Front End Training

1 week

Total

4 weeks



Growth Cloudscape Starter Kit

Project Phase

Duration

On-boarding + Strategy Call 

3 days

Data Gathering + Receive Data  

2.5 weeks 

Data Implementation 

3 days 

Back End/ Front End Training

1 week

Advance Reporting + Advance promotion Training

2 days

Xero Integration

1 week

Total

6 weeks + 1 week buffer




Advance Cloudscape Starter Kit

Project Phase

Duration

On-boarding + Strategy Call 

3 days

Data Gathering + Receive Data  

2.5 weeks 

Data Implementation 

3 days 

Back End/ Front End Training

1 week

Advance Reporting + Advance promotion Training

2 days

Xero Integration + Training

3 week

Total

8 weeks + 1 week buffer



Notes :


  • Phases will have traffic lights - Green Red

  • Project level traffic light will change Yellow once the phase level traffic light turns Red

  • Milestone “Mid Project check Point” to be added in Project Plan 

  • Due Dates to be added for every phase in the project plan

  • A field in Kanban View for the midpoint will be maintained in Asana